Project Updates
McLaren Group Picnic Area and Playground Project Update 11/10!
We will be removing two additional trees that are . . .
Read on at sfrecpark.orgGeorge Christopher schedule update 11/5!
The ball field fence repairs are complete and look fantastic!
Read on at sfrecpark.orgBay View Playground Renovation, update 11/02!
Demolition is in full force as most of the structures have been removed . . .
Read on at sfrecpark.orgGolden Gate Park Tennis Center Project Update 11/4!
Check out the great article on the project . . .
Read on at sfrecpark.orgCheck out the Discussion on South Ocean Beach Project with SPUR
Check out the panel discussion on the project . . .
Read on at sfrecpark.orgGolden Gate Heights Playground Construction Update 10/29!
Hi everyone- The construction fences are going up at Golden Gate Heights. . .
Read on at sfrecpark.orgGolden Gate Park Golf Clubhouse Project Update 10/29!
Planning and Design for the Golden Gate Park Golf Clubhouse Project is . . .
Read on at sfrecpark.orgHerz Playground Project Update 10/29!
Thank you so much to those who joined us for our final community meeting.
Read on at sfrecpark.orgHerz Recreation Center Project Update 10/29!
Hi everyone- We have been busy working with the project architects to . . .
Read on at sfrecpark.orgRossi Pool Project Update 10/28!
Much progress has been made over the past couple months on the utilities, sitework and interiors. . .
Read on at sfrecpark.orgEsprit park Project Update 10/29!
Hi everyone - We are getting organized for a virtual community workshop . . .
Read on at sfrecpark.orgMcLaren Park Redwood Grove Playground is Open for Play!!!
Hi everyone- We are officially open for play! Woohooo!
Read on at sfrecpark.orgJackson Playground Planning Update 10/29!
The project team is working on developing an overall project budget and securing agency approvals. . .
Read on at sfrecpark.orgGarfield Pool Renovation Update 10/27!
The major construction activities have been completed and we are near the finish . . .
Read on at sfrecpark.orgMargaret Hayward Project Update 10/20!
We still have many utility inspections to go; however . . .
Read on at sfrecpark.orgJerry Garcia Amp - Construction Slated to Begin November 2020!
The project has been advertised and we plan to award the contract this month . . .
Read on at sfrecpark.orgChildren’s Play Area Now Open at West Portal Playground!
The contractor has a few minor items remaining . . .
Read on at sfrecpark.orgWe are excited to report that Bay View Playground Renovation has started - 10/13!
Construction fences were installed last week to prepare for demolition next week.
Read on at sfrecpark.orgFillmore/Turk Mini Park Project Update 10/13!
So much to report!
Read on at sfrecpark.orgGeorge Christopher play equipment installed, fence work underway, and planting!
The play equipment is now installed at George Christopher!
Read on at sfrecpark.orgSgt. John Macaulay Playground ready for opening!
The site is getting final touches to be ready for opening . . .
Read on at sfrecpark.orgPortsmouth Square Schematic Design Complete! (10/13)
The project has reached an important milestone as schematic design wraps up. . . .
Read on at sfrecpark.orgGene Friend Rec Project Update 10/9!
Gene Friend Recreation Center has been included as a project . . .
Read on at sfrecpark.orgGeneva Powerhouse Project Update 10/9!
We are excited to announce that our tenant . . .
Read on at sfrecpark.orgMerced Heights Playground Lower Lawn Terrace Project Update 10/9!
A community meeting was held in November 2019 to review preliminary designs for a . . .
Read on at sfrecpark.orgMerced Heights Lower Lawn Terrace Project Update 10/9!
A community meeting was held in November 2019 to review preliminary designs . . .
Read on at sfrecpark.orgWest Portal Playground Project Update 10/8!
The restored field, as well as the nature exploration area, picnic area, and clubhouse restrooms, are now open . . .
Read on at sfrecpark.orgOcean Beach Climate Adaptation Project Update 10/7!
Planning and design is ongoing for this project . . .
Read on at sfrecpark.orgVisitacion Avenue Crossing Project Update 10/7!
We are awaiting bid results for this project . . .
Read on at sfrecpark.orgFrancisco Park Construction Update 10/7!
Francisco Park construction is moving along at a rapid pace . . .
Read on at sfrecpark.orgBuena Vista Park Needs Assessment and Cost Estimate Update 10/7!
A presentation of the Needs Assessment . . .
Read on at sfrecpark.orgGolden Gate Park Stanyan Edge Project Update 10/7!
Wanted to give a quick update on the this project. . .
Read on at sfrecpark.orgGolden Gate Park Tennis Center Project Update 10/7!
The Tennis Center construction continues to move forward with finishes and technology . . .
Read on at sfrecpark.orgBay View Playground Construction is just about to start!
The perimeter fences were installed last week and pre construction preparations are in place for demolition. . .
Read on at sfrecpark.orgMargaret Hayward Project Update 10/5!
The construction completion getting closer, but not quite ready yet…..
Read on at sfrecpark.orgHerz Playground Project Final Community Meeting!
Join us to see the updated design for Herz. . .
Read on at sfrecpark.orgMiddle Lake Design Pushing Forward 9/21!
The talented design team for the Middle Lake Rehabilitation is nearing completion of the 50% design phase. . .
Read on at sfrecpark.orgJuri Commons Construction continues 9/21!
Demolition is nearing completion and the Juri Commons Renovation is underway. . .
Read on at sfrecpark.orgRichmond Playground Concept Design Moving Forward 9/21!
Thank you so much to all who attended the third and final community workshop and to all who have contributed feedback along the way. . .
Read on at sfrecpark.orgMcLaren Group Picnic Area and Playground Project Update 9/18!
Hi folks- We have completed installing the new table tops and barbecues. . .
Read on at sfrecpark.orgWillie “Woo Woo” Wong Playground Update 9/18!
The Willie “Woo Woo” Wong project is quickly approaching completion! Here are a few recent photographs from the site.
Read on at sfrecpark.orgGolden Gate Heights Playground Construction Has Begun!
Hi folks- Construction has officially begun on the project!
Read on at sfrecpark.orgHerz Recreation Center Project Update 9/18!
Hi folks- The project team has been working to incorporate all the community feedback that we heard this summer. . .
Read on at sfrecpark.orgEsprit park Project Update 9/18!
Hi all- We are planning for additional community outreach this Fall. . .
Read on at sfrecpark.orgConstruction is Completed for the Stanyan Street Edge of Golden Gate Park!
If you haven’t noticed yet, all the construction fencing has been removed on the project that the public should have full access to the east edge of the park. . .
Read on at sfrecpark.orgHerz Playground Project Update 9/18!
Hi all- Our project designers have been updating the playground design to reflect the survey results on the play equipment…
Read on at sfrecpark.orgGuy Place Project Update 8/21!
Hi all- This will be our last blog update for the project.
Read on at sfrecpark.orgGeorge Christopher Playground project Update 8/21!
There has been tremendous progress on George Christopher Playground Renovation this summer. . .
Read on at sfrecpark.orgGolden Gate Heights Construction Starting Soon!
Hi everyone- We are getting close to the official start of construction!
Read on at sfrecpark.orgHerz Rec Center Project Update 8/21!
Hi everyone! Thanks to those who participated in our focus group meetings. . .…
Read on at sfrecpark.org