Gene Friend Rec Center | Construction update: Weekend Work on 3/1 & 3/8 + Night Noise Timing Updates
Please be advised that we anticipate that, weather permitting, the Contractor team will be working this Saturday, March 1, as well as the following Saturday, March 8, from 7 am to up to 7 pm. While performing this work, the contractor will continue to…
Read on at sfrecpark.orgTrocadero Clubhouse | Historic Trocadero Clubhouse Reopens After Repairs Completed
Following a two-year closure from storm damage, the landmark building is once again available to host weddings and other celebrations…
Read on at sfrecpark.orgBernal Heights Playground | Project update, February 2025
Thank you to everyone who stopped by our two community outreach sessions at the playground in January! We received a lot of helpful input through our survey and from those conversations with you. Based on what we heard, we are currently working with…
Read on at sfrecpark.orgEmbarcadero Plaza and Sue Bierman Park Renovation Project | Community Meeting, Thursday, March 6
We want to hear from you! San Francisco Recreation and Park Department invites you to participate and give input on the future of Embarcadero Plaza! Through public-private partnership with BXP and Downtown SF, the city is looking to refresh the brick and…
Read on at sfrecpark.orgKezar Pavilion Renovation Project | UPDATE: Concept Design review moved to April Commission meeting
MEETING UPDATE: The Kezar Pavilion Concept Design agenda item was moved to the Recreation and Park Commission meetings in April. In April, RPD staff will be presenting the concept design for the Kezar Pavilion Renovation Project to the…
Read on at sfrecpark.orgGene Friend Rec Center | Weekend Work on 2/22, 3/1, and 3/8 + Night Noise Permit for 3/3-3/7
Please be advised that we anticipate that, weather permitting, the Contractor team will be working this Saturday, February 22, as well as the following Saturday, March 1, and then Saturday, March 8, from 7 am to up to 7 pm. While performing…
Read on at sfrecpark.orgTwin Peaks Trail Improvement Project and Promenade Project | Construction update, February 2025
Exciting changes are coming to the connector trail between Crestline Drive and Twin Peaks Boulevard. Construction is set to begin soon, and the trail is now officially closed while work is underway. In the next two weeks, Cazadoro Construction will…
Read on at sfrecpark.orgRachele Sullivan Park | San Francisco Arts Commission’s Civic Design Review on February 24 at 11am
Rachele Sullivan Park Project (11th and Natoma) is scheduled to be presented at the San Francisco Arts Commission’s Civic Design Review on Monday, February 24, 11 am – 1 pm. There will be an opportunity for public comment following the presentation…
Read on at sfrecpark.orgEmbarcadero Plaza and Sue Bierman Park Renovation Project | Community Meeting, Thursday, March 6
We want to hear from you! San Francisco Recreation and Park Department invites you to participate and give input on the future of Embarcadero Plaza! Through public-private partnership with BXP and Downtown SF, the city is looking to refresh the brick and…
Read on at sfrecpark.orgGene Friend Rec Center | Weekend Work on 2/15 and 2/22 + Night Noise Permit for 3/3-3/7
Please be advised that we anticipate that, weather permitting, the Contractor team will be working this Saturday, February 15, as well as the following Saturday, February 22, from 7 am to up to 7 pm. While performing this work, the contractor will…
Read on at sfrecpark.orgBuchanan Street Mall | Panel Discussion on Black Public Art in SF + Paid Opportunities for Youth
We’re pleased to share two upcoming opportunities to participate in the development of the Memory Walk at Buchanan Street Mall. Join legendary artists Dana King, Kristine Mays, and Malik Seneferu in a panel discussion moderated by Adrian Owens and…
Read on at sfrecpark.orgRandolph and Bright Mini Park Improvements Project | Project update, February 2025
We’re excited to announce two upcoming opportunities to join SF Rec & Park for discussions about the planned improvements to Randolph and Bright Mini Park. During these sessions, Rec Park will present two concept plans for the site, featuring a nature…
Read on at sfrecpark.orgEsprit Park | Construction update, February 2025
Portions of the path along Indiana Street may be temporarily closed for the installation of light poles and decorative string lighting. This work began last week and is anticipated to be completed by the week of February 24. Impact to park users should…
Read on at sfrecpark.orgJapantown Peace Plaza Renovation | Construction update, February 7, 2025
When the rain slows down waterproofing work, our contractor focuses on preparing various mock-ups for approval. Our Pagoda mock-up will receive Fiber Reinforced Polymer (FPR) wrapping and tension rods this month. This will be evaluated by the design team…
Read on at sfrecpark.orgTenderloin Recreation Center Playground | Design Update, February 2025
Tenderloin Rec Center Playground Project Moves Forward with Unanimous Approval! We’re thrilled to announce that the San Francisco Recreation and Park Department Commission has unanimously approved the concept plan for the Tenderloin Rec Center Playground…
Read on at sfrecpark.orgEsprit Park | Dogpatch Neighbors Rejoice as Esprit Park Renovations Unveiled
The park’s first major renovation will ensure it remains an urban oasis in the heart of the dynamic Dogpatch neighborhood…
Read on at sfrecpark.orgGene Friend Rec Center | Construction update: Weekend Work on 2/8 + Night Noise Permit for 3/3-3/7
Please be advised that we anticipate the Contractor team will be working this Saturday, February 8, from 7 am to up to 7 pm. Since our last update, night noise permit dates are now 2/24-2/28…
Read on at sfrecpark.orgBuena Vista Park Improvements | Project update, February 2025
This project is currently in the planning phase, which includes mandatory regulatory and compliance work, as well as important on-the-ground testing to inform the design. Planning often appears quiet to park-goers, but things are very active behind-the…
Read on at sfrecpark.orgLet’sPlaySF! Initiative | Let’sPlaySF! Playground Survey extended to Friday, February 28!
Survey extended through the end of February! Thanks to the successful Let’sPlaySF! Initiative funded by the 2012 Park Bond, SF Parks Alliance, and philanthropic partners we are renovating 13 dilapidated playgrounds across our city. With 11 playgrounds…
Read on at sfrecpark.orgCrocker Amazon Baseball and Softball Fields Renovation | Community meeting on February 20, 6-7:30pm
Join the San Francisco Recreation and Parks Department to discuss the renovation of the baseball and softball fields at Crocker Amazon. The San Francisco Giants organization approached the Department with a proposal to partner to install six baseball and…
Read on at sfrecpark.orgKezar Pavilion Renovation Project | UPDATE: Concept Design review moved to April Commission meeting
MEETING UPDATE: The Kezar Pavilion Concept Design agenda item was moved to the Recreation and Park Commission meetings in April. In April, RPD staff will be presenting the concept design for the Kezar Pavilion Renovation Project to the…
Read on at sfrecpark.orgGene Friend Rec Center | Construction update: Weekend Work on 2/1 + Night Noise Permit for 3/3-3/7
Please be advised that we anticipate the Contractor team will be working this Saturday, February 1, from 7 am to up to 7 pm. While we have encountered several challenges with obstructions in the soil, we have worked collaboratively with the design and…
Read on at sfrecpark.orgKezar Pavilion Renovation Project | Project update, January 2024
MEETING UPDATE: The Kezar Pavilion Concept Design agenda item was moved to the Recreation and Park Commission meetings in April. In April, RPD staff will be presenting the concept design for the Kezar Pavilion Renovation Project to the…
Read on at sfrecpark.orgTrocadero Clubhouse | Construction update, January 2025
Getting closer! Our operations staff are putting on the finishing touches to make sure our beloved Trocadero is ready for public use. Stay tuned for an update about the project’s completion, which should be coming soon…
Read on at sfrecpark.orgStern Grove Playground Renovation | Construction update, January 2025
The contractor is currently focused on replacing the fencing along Sloat Avenue and completing the final stages of boulder placement within the playground…
Read on at sfrecpark.org