Background

On August 23, 2021, San Francisco Public Utilities Commission (SFPUC) crews were fixing a leaking air valve on a 54-inch pipeline when the air valve casing failed. Water spewed into air and into adjacent areas, including Sigmund Stern Grove.

SFPUC undertook a series of emergency contracts to repair damage done. This included removal of debris, restoration of any buildings damaged by mud and water, and stabilization of the hillside.

Budget Approximately $4 million

Project Schedule

Construction: August 2021 - Late 2023

Visit SFPUC’s Project Website for more information.

Get Out and Play!

Thanks for supporting park improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews . If you would like to receive updates about all our active capital improvement projects, please visit the News Flash section of our webpage and subscribe to “Rec Park Improvements | All Project Updates,” or pick-and-choose your subscriptions by project name.

You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!