Noe Valley Town Square Restroom Project
Completed and Opened to the Public in April 2024!
Scope of Work
The addition of a modular single-user all-gender accessible restroom at Noe Valley Town Square, site improvements, landscaping, and beautification.
Background
Noe Valley Town Square (NVTS) is located at 3861 24th Street (between Sanchez and Vicksburg Streets) on the 24th Street commercial corridor. The site is .25 acres and is surrounded by a mix of retail shops and services, restaurants, and multi-family and single-family residences. The property was purchased by RPD in June 2013 and the concept design was approved by the Recreation and Park Commission in 2014. The proposal to establish a public open space at the site evolved through more than four years of collaboration between the Department the community group Residents for Noe Valley Town Square, then-Supervisor Scott Wiener’s office, and the San Francisco Parks Alliance. NVTS opened to the public in October 2016.
The approved 2014 concept plan contemplated a public restroom in the northeast corner of the plaza. Due to funding constraints at that time, the restroom element was removed from the project. Since then, the Department allocated funds in the FY 21-22 budget for project planning including evaluating the viability of a modular restroom at the site and preparing cost estimates for project funding. Before that work began, the Noe Valley community successfully advocated for State funds for the project. Their ask was based on a high-level budget estimate for a custom-built restroom at the site.
In November 2022, the Department was approached by Vaughan Buckley with Volumetric Building Companies and Chad Kaufman with Public Restroom Company, who expressed interest in contributing a prefabricated modular restroom to Noe Valley Town Square.
In addition, RPD hired an as-needed landscape design firm to supplement the donor’s design drawing package. These drawings include all work associated with site improvements. These plans include demolition, grading, paving, fencing, irrigation and landscape. RPD drawings include the donor drawings which detail the restroom building and all associated mechanical, electrical and plumbing work.
The addition of a restroom to Noe Valley Town Square was approved by the Planning Department and found to be consistent with the project’s categorical exemption under CEQA. The Civic Design Committee determined that this project would be reviewed under their administrative process. The Recreation and Park Commission approved the acceptance of the restroom and site improvement gift in February 2023 and the Board of Supervisors approved the gift acceptance in April 2023.
Funding
- In-kind Grant Funding
- City Funding
- State Grant (pending)
Project Schedule
Phase Timeline
Planning | January - March 2023 |
Design | April - May 2023 |
Bid/Award | June - July 2023 |
Construction begins | February 2024 |
Open to the public | April 2024 |
Project Updates If you would like to sign-up for Project Update blog posts like the ones below, click here , scroll down to the News Flash section, and then select “RPD Park Improvements | All Project Updates” to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. You’ll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.