Golden Gate Park - Stanyan Street Edge Project
Completed and Opened to the Public Fall 2020!
Background
The eastern edge of Golden Gate Park was in need of improvements; the goal of the project was to make improvements to pedestrian access and circulation while trying to activate the area with positive park-related activities. The project goal also included making improvements to various landscape areas so that they are more inviting to visitors while protecting this beautiful landscape.
Scope of Work
This project was focused on making improvements to various areas on the Stanyan Street Frontage in Golden Gate Park. The areas of focus included renovating the Stanyan Street entry plaza, adding a new pedestrian sidewalk between Haight Street and JFK Drive, making landscape improvements in the oak woodlands area south of the lake and improvements to the existing restroom building and converting this space to a functioning kiosk which is now occupied by local business Flywheel Coffee.
Funding
This project was funded by the 2012 Clean and Safe Neighborhood Parks Bond.
The construction contract award for this project was approved by Recreation and Parks Commission on May 1, 2019 ( PDF ). This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project’s funding sources.
Get Out and Play!
Thanks for supporting park improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews . If you would like to receive updates about all our active capital improvement projects, please visit the News Flash section of our webpage and subscribe to “Rec Park Improvements | All Project Updates,” or pick-and-choose your subscriptions by project name.
You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!
Project Updates
SF Rec and Park Breaks Ground on Outdoor Fitness and Recreation Area for Seniors in Golden Gate Park
Community-shaped project will bring a model popular around the world to the Golden Gate Park Senior Center…
Read on at sfrecpark.orgGolden Gate Park-Senior Center Outdoor Recreation Area | Groundbreaking ceremony, October 6, 2 PM
Join Rec and Park and community members for a groundbreaking ceremony for a new outdoor recreation area at the Golden Gate Park Senior Center (6101 Fulton Street) on Tuesday, October 6 from 2 to 3 p.m. The project will add fitness equipment, seating and…
Read on at sfrecpark.orgGolden Gate Park-Senior Center Outdoor Recreation Area | Construction update, September 28, 2026
Construction will begin Wednesday, October 7. The driveway adjacent to the building will close to vehicles and pedestrians starting October 6 and will remain closed for the duration of the project. During construction, the parking lot behind the…
Read on at sfrecpark.orgDocuments and Materials
Community Meeting 3
Community Meeting Number 3 Presentation (PDF)
Community Meeting 2
Community Meeting 1
Award of Contract
Item 2 GGP Stanyan Street Frontage Improvement Project Award of Contract Staff Report 050119