Golden Gate Park - Botanical Garden Bookstore Barrier Removal Project
Completed and Opened to the public October 2024!
Scope of Work

This project designed and constructed a ramp and handrails to ensure that the Botanical Garden Bookstore complies with the Americans with Disabilities Act (ADA).
Background
In late 2021, Recreation and Park Department staff received a citizen complaint about access into the bookstore because it had one step up into the facility and no handrail or ramp. RPD’s ADA Coordinator for Physical Access and staff from the Mayor’s Office on Disability performed a site visit and confirmed the site conditions. Staff adopted a programmatic solution to accommodate patrons until the ramp and handrails could be completed.
Funding
Funding for the current scope of work will be allocated from RPD’s annual set-aside for ADA improvement projects.
Project Schedule
Planning , Early 2023
Design , Mid 2023
Construction begins , Mid 2024
Open to the Public , October 2024
Get Out and Play!
Thanks for supporting park improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews . If you would like to receive updates about all our active capital improvement projects, please visit the News Flash section of our webpage and subscribe to “Rec Park Improvements | All Project Updates,” or pick-and-choose your subscriptions by project name.
You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!
Project Update
Golden Gate Park - Blue Heron Boatshed | Project update, July 2026
Blue Heron Lake in Golden Gate Park is a 12-acre lake with an island in the middle, where hundreds of park visitors come to boat every week. Unfortunately, the on-water boat storage shed where rental paddleboats and rowboats are kept is now in…
Read on at sfrecpark.orgKezar Pavilion Renovation Project | Project update, June 2026
We are in the process of evaluating the proposals received for the CM/GC contract. We will make an announcement once the contractor is selected! We anticipate resuming the design phase of the project this Fall…
Read on at sfrecpark.orgGolden Gate Park-Senior Center Outdoor Recreation Area | Project update, June 2026
We’re pleased to report that we’re now more than halfway through the design process. We’re aiming to complete design work in the next few months and begin construction of the new outdoor recreation space this fall, once all the big concerts on the…
Read on at sfrecpark.org