Golden Gate Park - Blue Heron Lake (Stow Lake) Perimeter Path Renovation
Opened to the public September 2023!
Scope of Work
Blue Heron Lake is popular destination in Golden Gate Park for strolling, boating and picnicking. Before construction, the asphalt path that circles the perimeter of the lake had deteriorated and was in need of repair.
Th is project renovated the Blue Heron Lake perimeter path and site furnishings, including benches and picnic tables to achieve ADA compliance. The construction was performed in two phases so half of the perimeter path was open at all times.
Funding
This project was funded by multiple sources including the following:
- Recovery Stimulus and Critical Repairs
- General Fund
- Mayor’s Office on Disability
The construction contract award for this project was approved by Recreation and Parks Commission on August 3, 2022 ( PDF ); This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project’s funding sources.
Project Schedule
Phase | Timeline |
Planning | Spring 2014 |
Design | Summer 2018 |
Construction contract awarded | August 3, 2022 |
Construction | Spring 2023 |
Open to the public | Fall 2023 |