Golden Gate Park - 9th & Lincoln Gateway
Completed and Opened to the public on November 1, 2024!
Scope of Work
This project focuses on improvements to the road and landscape on the north side of the intersection at 9 th Avenue and Lincoln Way, with a symmetrical design encompassing both the east and west sides of 9th Avenue. These improvements include:
- Approximately 5,500 square feet of new concrete paving and plaza space
- Distinctive trees and landscaping in approximately 6,000 square feet of new planting area with upgraded irrigation
- New signage, including a large engraved boulder
- Large stone planters
- Stone steps with handrails
- New pedestrian lighting
- Relocation of the MUNI bus shelter farther west
- New curb ramps at both corners of the intersection
- Electrical and utility upgrades
Background
The gateway at 9th Avenue and Lincoln Way is one of the most well-used entrances to Golden Gate Park. Improvements to the gateway have long been a community priority and it was identified for a new entry treatment in the 1998 Golden Gate Park Master Plan.
The proposed gateway design will improve wayfinding and pedestrian safety for those arriving by foot, improve visibility of the park and botanical garden, and will serve to strengthen the connection between Golden Gate Park and the Inner Sunset. The materials selected for the new gateway ensure that it will be built to last for generations. New landscape improvements will create an iconic and welcoming arrival so that the entry experience will live up to its prominent location.
Funding
This project is funded through with revenue from the Open Space Fund and the General Fund:
- General Fund: $2,825,539
- Open Space Fund: $248,107
- Total funding: $3,073,646
The construction contract award for this project was approved by Recreation and Parks Commission on July 20, 2023 ( PDF ). This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project’s funding sources.
Project Schedule
Planning , 2016
Design , 2020
Construction contract awarded , July 20, 2023
Construction begins , Late 2023
Open to the Public , November 1, 2024
Get Out and Play!
Thanks for supporting park improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews . If you would like to receive updates about all our active capital improvement projects, please visit the News Flash section of our webpage and subscribe to “Rec Park Improvements | All Project Updates,” or pick-and-choose your subscriptions by project name.
You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!
Project Updates
Golden Gate Park - 9th and Lincoln Gateway | Construction complete
The 9th & Lincoln Gateway Improvements are complete. Thank you for your support throughout construction. This will be our last blog update for this project. Please visit our park improvements webpage to learn about other major projects happening in the Read on…
Mayor Breed Joins Inner Sunset Community to Celebrate Improved 9th & Lincoln Gateway
The $3 million renovation project, the latest in a series of enhancements to make the park more welcoming, accessible, and safe for all visitors, links Golden Gate Park to the bustling Irving Street commercial corridor Read on…
Golden Gate Park - 9th and Lincoln Gateway | Ribbon cutting ceremony, November 1, 11 AM to 12:30 PM
Join us for the reopening of the 9th & Lincoln Gateway in Golden Gate Park! Ribbon cutting ceremony followed by a reception at the Thomas Church Pavilion Celebration Garden at the San Francisco Botanical Garden. Read on…
View All /CivicAlerts.aspx
Documents and Materials
Commission Materials
- Rec Park Commission, staff report, Golden Gate Park 9th Avenue Gateway – Contract Amendment, August 15, 2024 (PDF)
- Rec Park Commission staff report - Golden Gate Park 9th Avenue Gateway – Contract Award, July 20, 2022 (PDF)
- Rec Park Commission staff report - GGP 9th and Lincoln Gateway Improvements, February 5, 2020 (PDF)
Additional Project Documents