Fillmore Turk Mini Park
Completed and Open to the Public in December 15, 2023!
Background
The Fillmore-Turk Mini Park community, under the new name of New Community Leadership Foundation, initiated improvements when they received a Community Opportunity Fund (COF) award of $330,000 for the park. COF is a program of the 2012 Clean and Safe Neighborhood Parks Bond. In 2019, Supervisor Brown committed $100,000 from the General Fund towards the project. In 2020, SF Beautiful received a Community Challenge Grant award of $100,000. With additional funding from 2012 Clean and Safe Neighborhood Parks Bond, General Fund, Open Space Funds and pro-bono design services from TS Studio, Landscape Architects this project budget is just over one million dollars.
Scope of Work
This 2012 Bond Community Opportunity Fund (COF) Project at Fillmore Turk Mini Park will revitalize the park with new landscaping, drainage, seating within the park.
Funding
Total project budget is just over one million dollars, including:
- Community Opportunity Fund (COF) award, 2012 Clean and Safe Neighborhood Parks Bond: $330,000
- General Fund: $100,000
- SF Beautiful Community Challenge Grant award: $100,000
- Pro-bono design services from TS Studio, Landscape Architects
The construction contract award for this project was approved by Recreation and Parks Commission on August 3, 2022 ( [PDF](http://Fillmore Turk Mini Park Renovation – Contract Award) ); Recreation and Parks Commission approved a contract amendment on October 12, 2023 ( PDF ). This construction contract award obtained and complies with all city, state, and federal regulatory approvals, including any that are specific to this project’s funding sources.
Project Schedule
Planning , Fall 2018
Design , Mid 2019
Construction contract award , August 3, 2022
Construction begins , Fall 2022
Open to the Public , December 15, 2023
Get Out and Play!
Thanks for supporting park improvements in your San Francisco parks! To stay informed and involved, we encourage you to subscribe to Rec and Park eNews . If you would like to receive updates about all our active capital improvement projects, please visit the News Flash section of our webpage and subscribe to “Rec Park Improvements | All Project Updates,” or pick-and-choose your subscriptions by project name.
You can also explore Rec and Park volunteer opportunities – We have park needs in every corner of the city and volunteer opportunities that are as diverse as your interests, skills, and abilities. Have fun in your parks, and get out and play!
Documents and Materials
Commission Materials
- Rec Park Commission staff report - Fillmore-Turk Mini Park Renovation – Contract Amendment, August 17, 2023 (PDF)
- Rec Park Commission staff report - Contract amendment, October 12, 2022 (PDF)
- Rec Park Commission staff report - Contract award, August 3, 2022 (PDF)
- Rec Park Commission, staff report, Construction Contract Termination, February 17, 2022 (PDF)
- Rec Park Commission staff report, September 19, 2019 (PDF)
- Rec Park Commission staff report - donor recognition plan, September 4, 2019 (PDF)
- Rec Park Commission staff report - donor recognition plan, May 14, 2019 (PDF)
Additional Project Documents