Background

South Sunset Clubhouse rendering credit Paulett Taggart Architects

South Sunset Playground is a 4-acre park featuring ball fields, basketball and tennis courts, a playground, a paved multi-use play area and the clubhouse. The 2,000 square-foot single-story clubhouse includes a multi-purpose room, restrooms, a kitchen, and an office. The building was originally constructed in 1949, renovated in 1991, and is in need of repair to better serve the community.  The current tenant is Self-Help for the Elderly, and they currently provide hot meals and programming to over 200 seniors. The park site was included in the 2020 Health and Recovery G.O. Bond with the support of the District Supervisor and State Budget Specified Grant via Assemblymember Phil Ting.

Scope of Work

Planned improvements to the park include the reconfiguration and renovation of interior spaces in the clubhouse, access improvements, and beautification.

Funding

  • 2020 Health and Recovery G.O. Bond
  • FY22-23 State Budget Specified Grant.

Estimated Project Schedule

Planning , 2022

Design , 2023

Construction begins , 2025

Open to the Public , Mid 2026

Project Updates If you would like to receive updates the South Sunset Clubhouse Renovation, please visit the News Flash section of our webpage and subscribe to " Rec Park Improvements: South Sunset Clubhouse ." To receive updates about all our active projects, subscribe to “Rec Park Improvements | All Project Updates.”

Project Updates

South Sunset Clubhouse | Construction update, June 2026

South Sunset Clubhouse is nearing substantial completion! We are working on the finishing touches to make the clubhouse ready for Self Help for the Elderly to move back in July. This includes paving adjustments for accessibility and testing the new Read on…

South Sunset Clubhouse | Construction update, April 2026

New paint and interior tile work is almost finished. Subfloor waterproofing was installed and subflooring is being completed – our contractor will install cabinets and finish flooring work over the coming weeks. Concrete work at the facility is Read on…

South Sunset Clubhouse | Construction update, February 2026

On the roof of the main building, we completed the installation and painting of the soffits and rain gutters. In back, the base and columns of the new pavilion are now in-place, and the roof and site concrete will be installed soon. Inside the Read on…