Lake Merced Trail Improvements
Completed and Opened to the public December 2024!
Scope of Work
This project will be completed in two phases. The work around South Lake Merced (Phase 1) is adjacent to the John Muir Parking Lot on the west side of the Lake. It is comprised of perimeter path replacement, a new picnic area with tables, a new adult fitness terrace with benches, repaving of ADA parking spaces, new signage, a trash enclosure, and replacement drinking fountain. Additional improvements include landscaping and irrigation upgrades.
The work around North Lake Merced (Phase 2) will replace existing paths at the northwest corner of the lake from the intersection with Harding Boulevard to the Sunset Circle parking lot. A new ADA accessible asphalt path will be installed along with an adjacent stabilized soil path, which will provide a softer surface. Additional site improvements will include installing adult fitness stations, site furnishings and replacing ADA parking spaces in the parking lot.
Funding
- California Natural Resources Agency Grant: $1,000,000
- 2012 Clean and Safe Neighborhood Parks Bond Citywide Parks Program: $2,000,000
- 2012 Clean and Safe Neighborhood Parks Bond - Forestry Program: $1,000,000
- 2018 Parks Bond Act - Recreational Infrastructure Revenue Enhancement: $634,540
Total Sources: $4,634,540
Project Schedule
Phase | Timeline |
Planning | Fall 2017 |
Design | Winter 2021 |
Phase I, Construction | Late 2023 |
Phase I, Open to the public | February 14, 2024 |
Phase II, Construction | Early 2024 through Late 2024 |
Phase II, Open to the public | Late 2024 |
Project Updates If you would like to sign-up for Project Update blog posts like the ones below, click here , scroll down to the News Flash section, and then select “RPD Park Improvements | All Project Updates” to receive updates on all our active projects, or pick-and-choose your blog subscriptions by project name. Y ou’ll receive an email that includes a link to confirm your new subscription for each blog for which you sign-up.
Contact Us
Omar Davis
Project Manager Email Phone: 1-628-652-6644